Link to CROA&DR 3829.doc
Link to CROA&DR 3829.txt
CANADIAN RAILWAY OFFICE OF ARBITRATION
& DISPUTE RESOLUTION
CASE NO. 3829
Heard in
Concerning
CANADIAN PACIFIC RAILWAY COMPANY
and
TEAMSTERS
MAINTENANCE OF WAY EMPLOYEES DIVISION
DISPUTE:
Contracting out of the installation of switch heaters and associated propane tanks.
JOINT STATEMENT OF ISSUE:
During the
summer and fall of 2008, the Company used a contractor(s) to install switch
heaters and propane tanks at various locations on the Revelstoke Division. The
The
The
The Company
denies the Union’s contentions and declines the
FOR THE
(SGD.) WM. BREHL (SGD) K. HEIN
PRESIDENT MANAGER,
LABOUR RELATIONS
There appeared on behalf of
the Company:
K. Hein –
Labour Relations Officer,
D. Freeborn –
Manager, Labour Relations,
B. Szafron –
General Manager, Engineering West,
V. White –
Labour Relations Officer,
And on behalf of the
Wm. Brehl –
President,
D. W. Brown –
Counsel,
S. Brighton – Local Chairman, Revelstoke
A. R. Terry –
Local Chairman,
AWARD OF THE ARBITRATOR
At issue in this grievance is the application of section 13.2 of the collective agreement which reads as follows:
13.2 Work presently and normally performed by employees who are subject to the provisions of this wage agreement will not be contracted out except;
(a) When technical or managerial skills are not available from within the Railway; or
(b) Where sufficient employees, qualified to perform the work, are not available from the active or laid-off employees, and such work cannot be delayed until such employees are available; or
(c) When essential equipment or facilities are not available and cannot be made available at the time and place required (i) from Railway-owned property, or (ii) which may be bona fide leased from other sources at a reasonable cost without the operator; or
(d) Where the nature or volume of work is such that it does not justify the capital or operating expenditure involved; or
(e) The required time of completion of the work cannot be met with the skills, personnel or equipment available on the property; or
(f) Where the nature or volume of the work is such that undesirable fluctuations in employment would automatically result.
There is
little, if any, dispute with respect to the material facts in relation to this
grievance. in 2005 the Company engaged in a substantial expansion project to
increase freight capacity in the corridor between the Prairies and the
To some degree
the work in question was time sensitive, as the switch heaters, whose function
is to ensure that ice and snow do not impede the operation of switches, needed
to be securely installed and operational before the advent of the winter
season. The work in question was projected to begin on September 29th, to be
completed in early November of 2008. In fact, the work extended to
It is common
ground that the Company did give to the Union notice of its intention to
contract out the switch heater installation work. The notice was in fact sent
to the
The Company does not dispute that the grievors were qualified to perform the work in question, and that such work had been performed by them on a regular basis in the past. Essentially the Company’s position is that the sheer volume of work, including the installation of up to twelve new switch heaters, was simply in excess of what could be performed utilizing the bargaining unit members who, it does not appear disputed, were fully occupied on other assignments. It also does not appear disputed that the Company was, in any event, compelled to contract out the electrical work as well as backhoe and excavator operations for the project.
It appears that
when the
Upon a close examination of the work performed by the grievors, as well as by the contractor, the Arbitrator is compelled to conclude that the Company is correct in its assessment that it did not have the manpower available to complete the work in a timely fashion without resort to the contractor. Firstly, in the preparatory period, between July and September, the grievors were absent from work for vacation and other reasons for a total of some eighteen weeks. During the time of project in September and October Mr. Wood was off work for some three weeks on account of injury.
According to the Company’s records the contractor billed a total of 1,250 hours for the work performed. By the Company’s reckoning, dividing the total hours between the three switch heater maintainers would have occasioned some 416 hours of work to each of them over a seven week period, which amounts to some 59 hours of work per week.
On the whole, the Arbitrator is satisfied that the facts in the case at hand do suggest the same conclusion which was drawn in CROA 2005 where the Arbitrator concluded that sufficient employees and equipment were not available to perform the work which was the subject of that dispute. As does not appear disputed before me, during the whole of the period under review, the grievors were fully engaged, suffered no loss of earnings and in fact earned significant amounts of overtime in what is obviously a busy time of year.
For all of the
foregoing reasons the Arbitrator cannot sustain the position of the
(signed) MICHEL G. PICHER
ARBITRATOR